All articles
Permits & County··8 min read

Do You Need a Land Clearing Permit in Cochise County?

Clearing more than one acre in unincorporated Cochise County requires a permit. It costs $50, there are four exemptions worth knowing, and doing it without one is a Class 1 misdemeanour with daily penalties. Here is the whole thing in plain English.

Here is a thing worth noticing. Search "land clearing arizona" and the top result is not a contractor and not a guide — it is Cochise County's own land clearing ordinance page.

That tells you what people are actually trying to find out, and that the only thing available to answer them is a legal document. So here is the ordinance in plain English.

The threshold

Clearing more than one acre of land in unincorporated Cochise County requires a Clearing Permit. One acre or less does not.

That is the whole test. It is not about the machine you use, whether you are building, or whether you own the land. It is area.

For scale: one acre is 43,560 square feet. A square acre is about 209 feet on a side. A building pad, a driveway and a defensible-space margin on a typical residential build will often come in under an acre — and a plan to "clear the lot" on a four acre parcel very much will not.

The fee

$50 for the review and approval of a Clearing Permit.

It is worth pausing on that number, because it changes how you should think about the whole question. Fifty dollars is not a barrier. If you are anywhere near the line, apply. The cost of the permit is trivial next to the cost of getting it wrong, and it is trivial next to almost every other line on the job.

The four exemptions

The ordinance exempts:

  1. Clearing of one acre or less, for residential and non-residential purposes.
  2. Clearing for agricultural purposes, mining, and other uses exempted by A.R.S. § 11-830. That state statute limits what counties may regulate, and the agricultural exemption in particular is broader than people expect — but it applies to genuine agricultural use, not to describing your building site as a future orchard.
  3. Clearing for the maintenance of existing roads, private access easements, driveways and utility easements. Note the word existing. Maintaining a driveway you already have is exempt. Cutting a new one is not maintenance.
  4. Clearing for new public utilities exempted under Article 20 of the county zoning regulations.
"Existing" is doing real work in exemption 3

Brushing back an established two-track so a truck can get down it is maintenance of an existing access. Widening a footpath into a driveway, or cutting a new alignment because the old one crosses a wash, is new clearing and counts toward your acre. If you are unsure which side of that line your job sits on, call Development Services on 520-432-9300 before the machine arrives rather than after.

What the permit actually asks of you

Two operational requirements sit in the ordinance, and both are things a competent contractor should be doing regardless.

Dust control

Dust must be minimised using generally acceptable dust suppressants. The ordinance says something slightly surprising here: water, although generally accepted, is not preferred.

That reads oddly until you think about where you are. Water applied for dust control on a valley floor in June evaporates almost immediately, which means the suppression lasts minutes and you have used a scarce resource to achieve it. In a basin with an annual groundwater overdraft over 100,000 acre-feet, spraying potable water on dirt is a poor trade. The ordinance is nudging toward chemical suppressants, surface treatment, or simply not disturbing ground you do not need to disturb.

Erosion control

Erosion must be minimised using acceptable best management practices, and — this is the clause with teeth — your control measures must not alter existing drainage patterns or cause property damage off site.

Read that as written. It is not enough that water leaves your property. It is not enough that your pad is dry. If your clearing and grading changes where water goes and that damages a neighbour, that is a violation on top of whatever civil exposure comes with it.

This matters more here than the mild-sounding language suggests. Fifty-seven percent of the annual rainfall at Pearce–Sunsites arrives between July and September, and it arrives in cells that drop a lot of water quickly onto ground with very little cover. Freshly cleared ground with no erosion control ahead of monsoon season is the specific failure mode this clause exists for.

Practical measures on a residential-scale job: silt fence on the downslope edges of disturbed ground, straw wattles across any concentrated flow path, keeping native cover on everything you do not need to strip, and — most effective and least used — clearing less in the first place.

The penalties

Violations are misdemeanours. The ordinance sets fines of not less than $50 and up to the maximum allowed for a Class 1 misdemeanour, plus daily accruing penalties of up to $50 per day.

The daily accrual is the part that matters. This is not a one-off fine you can price into the job; it is a meter that runs while the condition persists.

Set that against a $50 permit fee and the arithmetic is not close.

The other permits people confuse this with

A clearing permit is one of four county approvals that can attach to early site work, and they are separate. Getting one does not get you the others.

PermitTriggered byIssued by
Clearing PermitClearing more than one acreDevelopment Services
Right-of-Way PermitDriveway access, culverts or utility work in county right-of-way. Fee starts at $100Engineering & Natural Resources
Floodplain Use PermitAny man-made change to property inside a designated floodplain — including grading and fill, and required even where no building permit is neededFlood Control District
Building PermitStructures above the exemption thresholdsDevelopment Services

The floodplain one catches people hardest, because it applies to grading and filling on its own. If your parcel is in a designated floodplain, you can need a permit to move dirt on land you have no intention of building on this decade.

How this shapes a sensible plan

Most residential jobs here do not need a clearing permit, and the reason is not that people are avoiding it — it is that clearing under an acre is usually the right answer anyway.

A building pad, a driveway alignment, a tank pad and a defensible margin around the structure is a real and generous amount of cleared ground. Stripping four acres because you own four acres is worse on every axis: it costs more, it removes shade you cannot buy back, it removes the native cover holding your soil in a July storm, it creates a maintenance obligation because bare ground colonises with tumbleweed, and it puts you over the threshold.

Clear what you need. If what you need is more than an acre, spend the fifty dollars.

If you are hiring somebody

Ask two questions before work starts:

  1. How many acres does this scope clear? Not the parcel size — the disturbed area. Get it as a number.
  2. Who is pulling the permit if one is needed, and is it in the quote?

A contractor who has not thought about the threshold on your job has not thought about the erosion clause either, and the erosion clause is the one that produces a neighbour with a damaged property and a claim.

We scope the disturbed area as part of every quote, tell you which side of the acre line it falls on, and handle the permit where one is needed. If you are trying to work out whether your plan crosses the threshold, send us the parcel number and an outline of what you want cleared.

Sources

Every number in this article traces to one of these. Rules and fees change — if you are reading this a year from now, check the source before you rely on the figure.

Working on a parcel in Cochise County?

We clear, grade and prep off-grid property across the Sulphur Springs Valley — building pads, driveways, trenching, tanks and solar. Tell us what you have and we will tell you what it takes.

Keep reading